Views: 165

Albums: Delack Log Home
Location: Orofino,Idaho

Comment by Lee Woolsey on December 9, 2011 at 8:36am

Martin, the mortar/tru-pak we applied here was typically 2" to 2½" thick. Generally we (2 of us) could do 60 - 70 square-feet per day; that was 5-6 hours of production time, including daily prep, clean-out of the previous days carve, staging materials and so forth. The site around the house was pretty rough (bull-rock and mud) so setting ladders and planks and running power took longer than usual. Due to the weather we'd also have to drain all of our hoses and similar chores daily.

Comment by martin jelic on December 9, 2011 at 2:07pm

Hi Lee,

Thanks for all your detailed responses. I thik even the most difficult thing is the color.

Comment

You need to be a member of The Vertical Artisans Forum to add comments!

Join The Vertical Artisans Forum

© 2024   Created by Nathan Giffin Vertical Artisans.   Powered by